New-build handover in Cyprus: inspection, snagging and reinspection

A practical guide to accepting a new home from a developer in Cyprus, covering inspection preparation, documenting defects and checking completed repairs.

New-build handover in Cyprus: inspection, snagging and reinspection

When your new home is ready for handover, it is tempting to collect the keys and start imagining life there. First, though, take time to walk through the rooms, compare the finished property with what you agreed to buy and discuss anything that still needs attention. Gather your documents beforehand so you are not searching for a contract clause or trying to remember an agreed appliance model during the visit.

A property handover involves preparation, inspection and a written record of the outcome. If defects are found, they need to be checked again after remedial work. For each issue, the record should make clear what was observed, what evidence supports it, who will arrange the work and how the result will be verified.

This guide follows that process for an apartment or house bought from a developer in the government-controlled areas of the Republic of Cyprus. Resale properties are different: a private seller’s obligations to remedy defects need to be assessed separately against the transaction documents.

Keep four outcomes distinct from the outset. A property inspection establishes the condition of the home within the scope of the checks performed. Contractual handover records what has been delivered to the buyer and which obligations remain outstanding. Lawful occupation and use depend on the applicable approval documents. Registration of ownership records the transfer of title. Receiving the keys gives you access to the property; workmanship, approval status and the transfer of ownership each require their own checks.

Preparing for a manageable handover

Start with the signed contract, the schedules covering fixtures and equipment, the plans and any agreed amendments. If a specialist has already inspected the property, bring the earlier report too. A finished interior should not distract from issues raised at a previous visit.

Mark the pages you are likely to need: the kitchen specification, the number of air-conditioning units or the parking space allocated to the apartment. Keep advertising material and correspondence alongside the contract. If the finished property differs from a promise, your lawyer can assess the significance of that difference.

Next, establish the conditions for the visit. Damage is easier to spot in a clean room, and water supply and drainage cannot be tested without a water connection. Before attending, find out:

  1. which rooms and common areas will be accessible;
  2. whether cleaning and installation are complete and surfaces are exposed for inspection;
  3. whether water and a safe, normal electricity supply are connected;
  4. who will receive your observations and agree remedial work on the developer’s behalf;
  5. how you can access the property for a reinspection.

If construction is still under way, agree access and a safe route separately. An inaccessible area remains uninspected, even if no issues were found elsewhere in the apartment.

When to involve a technical specialist

Some issues are easy to spot yourself: a scratched door, a missing appliance or a window sash catching on its frame. Establishing the cause of a crack or a stain below a window is more involved. A specialist can assess what is visible and determine what needs further investigation.

Agree the scope before the visit. Which rooms and systems will the report cover? What methods will be used? What falls outside the inspection? What does a return visit cost? These questions help align your expectations with the service you are buying.

If you appoint an engineer, you can check their name, registration number, discipline and annual licence for the current year through the register of ETEK, the Cyprus Scientific and Technical Chamber. The Greek-language page links to the list of professionals. After checking qualifications, agree the inspection scope, report limitations and return visit in writing. For electrical work, also confirm that the person is authorised to carry out the particular checks required.

Before commissioning the inspection, ask whether the specialist has ties to the developer or contractor, took part in the property’s design or supervision, and who will receive their findings. Discuss these relationships in advance. The service agreement should identify the client, the report recipient and the scope of work undertaken in your interests.

Assessment of load-bearing structures, electrical measurements and checks of concealed services should be expressly included in the specialist’s brief where required. Methods for investigating latent defects, including thermal imaging, should be selected to suit the issue and inspection conditions.

If you cannot attend in person

A representative can attend the handover, but they will need the same versions of the documents you use. Agree their authority with your lawyer in advance: inspecting the property, accepting replacement equipment and signing a handover document involve different decisions.

For example, your representative may notice that a different tap has been installed and add it to the snagging list. They can accept the substitution only if their authority permits it. A video call can help you discuss the finding during the visit, but it does not replace a technical inspection.

Checking what has been delivered under the contract

With the documents to hand, start by comparing the specified items with what is actually in the property. Work through them one by one and record any differences. An item being present, its installation being complete and its operation being tested are three separate outcomes.

Consider a few situations you might encounter.

The contract specifies two air-conditioning units, but only one is installed. Schedule 2, line 12, provides for two units of an agreed model. The second is missing at inspection. A snagging-list entry might read: “Second unit missing from bedroom; reference: Schedule 2, line 12; photograph of installation location attached.” Once the unit is fitted, its model still needs to be checked and its operation tested within the specialist’s brief.

The tap model changed after the contract was signed. If the parties agreed a replacement in signed amendment 2, compare the installed model against that amendment. A matching model resolves the specification question; installation quality and operation require separate checks.

You are shown parking space 19 instead of space 17. Record both numbers and ask for the basis of the substitution. Equal floor area does not necessarily make the spaces equivalent under the contract or in terms of the rights being acquired. Refer this to your lawyer before agreeing to a replacement.

You receive a brochure instead of an operating manual. If the contract requires manuals and warranty documents, a general manufacturer’s brochure does not replace the documents for the installed model. Record the appliance, the missing document and the person to whom the request is addressed.

This comparison gives you a clear picture of what matches the documents, what still needs to be supplied and what needs clarification. You can then move on to the condition of the property itself.

Working through the property without losing track

Finish one room before moving to the next. A simple route might be the entrance, living areas, kitchen, bathrooms, balcony or terrace, then the storage room, parking and common areas. Mark inspected areas on the plan and note anything that needs another visit.

Walls, ceilings and floors

The overall finish may catch your eye first, but a useful snagging entry needs a precise location: a crack, chip, stain or unfinished section. “Living room, wall to the right of the entrance, damage beside the skirting board” makes the issue easy to find again.

If packaging covers the floor or building materials obscure part of a wall, record those surfaces as uninspected. Return to them once the area is clear.

A technical specialist can help determine whether cracks or uneven surfaces are acceptable. They will select the relevant assessment criteria and measurement method in light of the property’s documents and requirements. A tolerance taken from someone else’s checklist may not apply to your home.

Doors and windows

Check the visible glass, frames, handles and seals. Open and close accessible doors and windows normally, without force, dismantling or attempting adjustments yourself.

If a sash catches on the frame, a short video can show what happens. For water marks below a window, take photographs and describe the conditions in which you observed them. Dry weather during the visit does not establish that the window will remain watertight in rain.

Kitchen, fitted furniture and appliances

Continue comparing the kitchen with the contract: are the correct appliances installed, are all components present, and are accessible surfaces undamaged? Check that cupboard doors and drawers move normally.

For appliances, record the model, serial number, availability of the manual and tests performed. An oven, for example, may be installed but not yet connected. Record exactly that: installation is visible, but operation has not been tested.

Bathrooms and wet areas

Look for visible water marks, damage, unfinished joints and missing items. Include checks of water supply, drainage, ventilation and waterproofing in the relevant specialist’s brief beforehand.

Do not flood-test a floor, balcony or terrace yourself. The test method must account for the property’s readiness and the risk of damage to finishes and neighbouring premises.

If water is not yet connected, record: “Water supply and drainage not tested; further access required after connection.” This keeps the outstanding check visible until the necessary conditions are in place.

Electrical installations and equipment

As a buyer, you can compare visible equipment, models, remote controls and documents with the specification. Leave opening the distribution board, dismantling equipment, electrical measurements, protective-device tests and load testing to a competent specialist.

If an electrical component is exposed or safety is uncertain, stop your own checks in that area and notify the developer’s representative. Take photographs only from a safe distance.

For air conditioning, heating and hot water, establish which operating modes were tested, by whom and under what conditions. “It switches on” does not establish that every function works.

Beyond the apartment door

By the end of a walk-through, it is easy to focus on the apartment and forget the rest of the purchase. Give the balcony, storage room, parking and common areas their own attention.

From a safe position, note damage, water marks and unfinished surfaces. Specialists should inspect barriers, gradients, drainage, the roof and façade with agreed safe access.

Check parking and storage identifiers against the documents. Keep a separate list for entrances, stairs, the lift, courtyard, pool and other specified facilities. If the courtyard is still under construction, record its actual condition, accessible routes and outstanding work. For the lift, pool and complex communal systems, establish separately who will inspect them and which documents are needed.

Matching the response to the issue

Your list may contain a scratched door, a missing appliance and a stain of unknown origin. Record two things separately for each: the type of issue and the urgency of action. Unfinished work can also present a danger, while apparently cosmetic damage may need investigation. Set priorities according to the effect on safety and use of the home.

If there is any sign of a possible hazard, stop checking that area yourself and involve the appropriate specialist. This applies to every type of issue. For example, do not shake a visibly damaged barrier to test its strength.

The issue itself can be described as follows.

Incomplete work or a missing item requires comparison with the specification and an agreement on completion. Urgency depends on how the missing element affects use and safety.

A functional fault, such as a door that will not close, requires a further functional check after repair. A specialist determines the cause and technical solution.

A cosmetic issue, such as a scratch, can be documented with a photograph and an agreed repair outcome. If you are asked to accept the damage as permissible, ask for the applicable criterion and its basis.

An unexplained sign, such as a damp stain, leaves the cause unresolved. Repainting alone may not be sufficient until that cause is established.

These categories help organise the list; the inspection provides the technical assessment. Your main contribution is a precise description of what you observed.

Turning a snagging list into a record of remedial work

Record issues during the inspection, while you can point out the location and discuss it with the representative. The resulting snagging list connects the initial observation with later work and reinspection.

At the start, include the address, apartment or house number, date and time, participants and their authority. Record the versions of plans and specifications, access conditions and any areas that could not be inspected.

Give each issue a permanent number, then build up its record with:

  1. The exact location and a description of what was observed.
  2. The basis for the expected result: contract, specification, plan or specialist’s findings.
  3. Photographs, videos and relevant reports.
  4. The recipient, date sent and confirmation of receipt.
  5. The agreed action and who will arrange the work.
  6. The agreed completion date, or a note that none has been agreed.
  7. The criterion for accepting the result and the method of checking it.
  8. The date, participants and outcome of the reinspection.

Take both a wider photograph to locate the issue and a close-up to show it clearly. Keep the original files and add post-repair photographs to the same entry. This preserves the sequence of changes.

The appointed tradesperson and the party responsible under the contract may be different. Check the transaction documents and consult your lawyer about the correct recipient and procedure for a formal claim.

Why a status tells you more than a tick

An unresolved issue stays open. You can add “sent” after notifying the recipient, “reported as repaired” after a repair update, and “awaiting reinspection” before the next visit. Use “closed after verification” alongside the result, date and name of the person who checked it.

“Not tested” deserves its own status, for example where a system has not been connected. Include the reason. If an item does not form part of your purchase, such as a separate garage, record “not applicable” and explain why.

If a check was completed and no issues were found within its scope, record that scope and outcome. Where the parties disagree, retain the item as disputed and preserve both positions. These distinctions show what is actually complete and what still needs a decision.

Agreeing timescales

Once issues are recorded, discussions with the developer can be specific. For each open item, agree the work, timing, access for the tradesperson and how you will be told it is complete.

A window might need adjustment by an agreed date, followed by a check that it opens and closes normally. Water marks may first require investigation. Separate diagnosis from repair where the cause, and therefore the scope of the work, is still unknown.

If a deadline has not been agreed, say so in the record. Your preferred date and a commitment accepted by the other party are different things.

Repair deadlines also differ from manufacturer’s warranties, notification deadlines and time limits for legal proceedings. Republic of Cyprus Law 66(I)/2012 sets out separate rules for contractual claims and other causes of action. A lawyer should determine the applicable limitation period and when it starts in the circumstances. Check warranty periods against their own terms. Limitation of Actions Law, sections 3, 6 and 7.

What to collect with the keys

After the inspection, the discussion usually turns to documents and access. Review contractual performance, approval documents, ownership registration and equipment operation separately. Each has its own outcome.

Approval documents

An apartment’s appearance does not establish its approval status. Your lawyer and the relevant technical specialist will need the actual documents and reference details. They should check which property each document covers, its scope and any annotations.

Section 10 of the Republic of Cyprus Streets and Buildings Regulation Law links occupation and use of a building or part of it to the competent authority issuing a Certificate of Approval. The law provides for approval of part of the works and a separate regime for certificates with annotations. What matters is the content of the document as it applies to your property. Law, Cap. 96, sections 10 and 10B.

After an application has been submitted, check that the certificate itself has been issued. If you are invited to move in, first ask your lawyer and technical specialist to verify which document permits use of your particular home and what it covers. Inspection, key handover and moving in are separate steps. Workmanship and specified items are checked against the contract; permitted use is checked against the approval documents.

Registration of ownership

Receiving the keys gives you access to the property. Completion of ownership registration is established through the records of the transfer of title. The Department of Lands and Surveys describes transfer as a separate procedure with its own required documents. Transfer procedure for a sale.

If registration is ongoing, establish whether a separate title deed exists, what has already been submitted and which step comes next. Application acknowledgements, known obstacles and contact details for the person responsible for the next step will help you follow progress after receiving the keys.

Manuals and warranties

Over time, you will need to know how to maintain each appliance, whom to contact if it fails and which terms apply. Collect manuals for the installed models, warranty documents and contact details at handover.

For building services, ask about the applicable commissioning and test documents, together with any available as-built drawings of the services. Record the exact name of each missing document.

Republic of Cyprus Law 142(I)/2006 provides for an Energy Performance Certificate (EPC) to be shown and handed over to the buyer, subject to applicable exceptions. The certificate describes energy performance; an inspection for building defects serves a separate purpose. Sections 6 and 8, Annex II.

Request the certificate if it has not been supplied. The duties to show and hand over the certificate relate to the construction and sale stages, so check that you have received it before key handover.

For each warranty, review what it covers, its start and end dates, exclusions and the claims procedure. Appliance warranties and obligations relating to the building may have different terms.

Keys, access devices and meter readings

Count the keys for the entrance, storage room, letterbox and other included spaces. You may also receive remote controls and electronic access cards. Record the quantity, purpose and result of checking access.

Photograph meter numbers and readings, recording the handover date. Separately clarify supply-account arrangements, current charges and the confirmations required. A photograph records the reading; outstanding balances and account transfers require their own documentation.

Reviewing the handover document

By the time you sign, you should have a clear picture of the property’s condition. The document you sign needs to reflect that picture.

Obtain a draft in advance. Discuss wording about full performance, absence of claims, settlement of a dispute or waiver of rights with your lawyer before signing, particularly if items remain open on the snagging list.

Your lawyer can advise how to record unfinished work in the handover documents and link it to the snagging list. Permanent item numbers and identical versions of the attachments help keep that link clear.

Decisions to postpone handover, decline to sign or withhold payment depend on the contract and applicable law. Consult your lawyer before changing payments: any permissible retention and the procedure must be determined from the terms of the transaction.

If the representative refuses to sign the snagging list, keep your own dated record, photographs, the package you sent and any reply. Ask your lawyer about the proper notification procedure. The absence of a joint signature is no reason to discard the material you have collected.

Reinspecting the remedial work

When you are told the repairs are complete, return to the same list. It lets you locate each issue, review the original agreement and check whether the required outcome has been achieved.

Imagine Anna inspecting her apartment with Pavel, the seller’s representative. After remedial work, they meet again and revisit the same issues.

Register details

  1. Property: fictional “Building 1”, apartment 5.
  2. Participants: buyer Anna and Pavel, representative of the selling company.
  3. Documents: plan 4, version 2; specification in Schedule 2, version 2.
  4. Inspections: initial inspection and reinspection after notification that work was complete.
  5. Register version: 2, following reinspection; original entries retained.

The bedroom window now closes

At the first inspection, the sash caught on the frame. It was checked again after adjustment, with the history recorded as follows:

  1. Reference: issue 1.
  2. Location and observation: bedroom, second window; sash catches on the frame and cannot be closed normally.
  3. Type: functional fault.
  4. Urgency: scheduled remedial work. If signs of danger appear, stop checking it yourself and contact the appropriate specialist.
  5. Basis and evidence: normal opening and closing required by specification clause 8; location marked on plan; initial photograph “01 — overview” and video “01 — closing”.
  6. Notification and receipt: Anna sent the entry to the selling company on the day of the first inspection using the agreed email address; Pavel acknowledged receipt by reply the same day.
  7. Agreed action and responsible organiser: Pavel to arrange adjustment by the seller’s tradesperson before the return visit; agreement retained in the email reply.
  8. Acceptance criterion and check: sash opens and closes normally without force; check by opening and closing it again on site.
  9. Reinspection: checked by Anna in Pavel’s presence during the return visit; sash opens and closes normally; video “01 — after adjustment” added.
  10. Outcome and next step: closed after verification against the agreed criterion; possible water ingress recorded separately under issue 2.

Anna is checking only normal opening and closing here. A specialist assesses the window’s construction and weather tightness.

The stain has been painted over, but the cause is still unknown

Issue 2 records a damp mark beneath the same window, with the cause yet to be established. An overview photograph and close-up were attached, with the location marked on the plan. Anna sent it to the seller with issue 1. Pavel acknowledged receipt and accepted the request to arrange an investigation.

Before the return visit, Pavel reported that the area had been repainted. However, no specialist had been appointed, and neither the timing nor priority of the investigation had been agreed. There were no findings on the cause and no agreed method for verifying that it had been resolved.

During the reinspection, Anna looked at the clean surface in Pavel’s presence and added another photograph. The issue remained open: the next step was to appoint a specialist and agree the investigation and method of checking the result. Unlike the window adjustment, the completed work had not yet answered the original question.

The air-conditioning unit is installed, but testing is outstanding

Issue 3 recorded the missing second unit, citing Schedule 2, line 12 of the contract. The representative agreed to have it installed before the return visit.

At reinspection, the unit was present and its model matched the specification. However, the specialist had not yet tested the operating mode included in the brief. Delivery and installation were recorded as complete. Operation remained “not tested”, with the outstanding mode identified for the specialist. The item was not fully closed.

The scratch has been repaired

Issue 4 concerned a scratch beside the handle on the inside of the bedroom door. At the initial inspection, it was photographed, repair before the return visit was agreed, and a further visual inspection was planned.

After the repair, the area was shown on site, inspected and accepted. A new photograph was added alongside the original, the result was recorded and the item closed.

A photograph of an electrical repair does not close the issue

At the first inspection, issue 5 recorded unfinished visible fittings at an electrical point. The buyer stopped checking that area, sent the representative a photograph taken from a safe distance and requested specialist assessment. No date for the necessary work had yet been agreed.

The contractor later sent a photograph of the repair, but the results of the required check by a competent specialist had not been received. The item remained open pending the results of the installation safety check.

These examples show why “everything is done” may not be enough. In the same apartment, some items may be closed, some awaiting verification and others still awaiting a diagnosis.

To plan your budget, use our calculator for the total cost of buying property in Cyprus.

If a defect appears after you receive the keys

One visit will not reveal everything. If a problem becomes apparent later, record the date, location, conditions and consequences promptly. For water marks, note whether it had been raining or equipment was in use. Bring together the contract, plans, snagging list, handover documents and earlier correspondence to establish the sequence of events.

Send notice to the correct recipient using the applicable procedure. An uncertain cause may require technical investigation; a dispute about obligations or deadlines may require a lawyer. If the problem has already appeared, do not wait for another season merely to collect further observations.

Where urgent action is needed for safety or to limit damage, seek competent help first. Where safe and practical, record the condition before work begins and retain documents showing what was done. Check the time limits for protecting your claim separately, even while repairs are being discussed.

What you should have at the end of handover

Before the meeting ends, review the snagging list once more. It should show which areas were inspected, which remained inaccessible, what matched the contract and which discrepancies were found.

Every open issue should have a reference number, evidence, a recipient and a next step. Distinguish agreed actions and dates from those still under discussion. Untested systems need arrangements for further access; repairs need a clear method of verification.

Record the documents received, keys handed over and meter readings. Before signing, check that the handover document reflects the property’s actual condition and the contract terms. Keep this package with its attachments and replies so you can return to unfinished matters without reconstructing them from memory.

A short checklist for the meeting

Tick off completed tasks. Beside anything outstanding, note what remains, who will arrange the next step and which date has been agreed. Mark inaccessible or unconnected items “not inspected” or “not tested”, as appropriate.

Contract, plans, specification and amendments collected.

Access and inspection conditions agreed; limitations recorded.

Specified items checked and discrepancies added to the snagging list.

Rooms and common areas inspected within the agreed scope.

Systems checked by specialists; results and limitations retained.

Approval status checked before deciding to move in; ownership-registration status clarified.

EPC, manuals and warranties received, or missing documents recorded.

Keys and remotes counted, access checked and meters photographed.

Handover document reviewed before signing and open issues reflected in it.

Actions, acceptance criteria and reinspection agreed for outstanding work.


FAQ

Can an inspection be completed without connected water or electricity?
You can inspect accessible surfaces and compare installed items with the specification. Unconnected systems will remain untested, so arrange further access. Whether handover can proceed, and any related payments, must be assessed separately against the transaction documents.
Are photographs of repairs enough to close an item?
A photograph can sometimes confirm that an item is present or show the appearance of a surface. System operation, installation safety or resolution of the cause of a leak may require a different check determined by a specialist. Use the agreed outcome as your reference.
What if the developer disputes an issue?
Keep the item marked as disputed, together with its basis, evidence and the response. The appropriate specialist can assess the technical disagreement; a lawyer can advise on the recipient, notification procedure and further claims.