Cyprus’s Department of Forests has launched a tender for the first phase of road improvements in Akamas National Forest Park. The €5.63 million project covers three routes totalling around 9.9 km and a car park near Lara. The article explains the procurement timetable, seasonal restrictions and what remains to be clarified before work begins.

Akamas road improvements move to tender with a €5.63 million first phase

Cyprus’s Department of Forests has launched tender ΤΔ 46/2026 for road improvements in Akamas National Forest Park in the Paphos district. The estimated value is €5.63 million excluding value added tax (VAT). Bids are due by 8 December 2026.

The contract covers three road routes with a combined length of around 9.9 km, together with a car park in the Lara area and its access road. The works are scheduled to take 13 months from the project start date. The procurement process is under way; contractor selection and contract signing are the next stages.

Official contract notice

What the Akamas road tender covers

The roads are listed in Volume E, Appendix 100/2 of the revised tender documents.

The longest route is Aspros Potamos–Toxeftra–Lara, designated 1A in the documents, at around 6.2 km. The Lara circular road, designated 2, accounts for approximately 2.7 km. A further section of around 1 km runs from Toxeftra to Avakas and is designated 4Bi.

The works also include a car park on plots 161, 162 and 163 of cadastral sheet/plan 34/39 in the Lara area, plus an access road. The 9.9 km figure is therefore the combined length of the three listed routes; it does not include an additional length for the car park access road.

On sections with a longitudinal gradient below 8%, the design specifies a surface layer of Type 1 road material with a polymer additive to increase its strength. Sections with a gradient above 8% are to receive concrete pavement.

The project also includes work on existing structures that carry water beneath the roads, reinforcement of selected sections and traffic management. For residents and businesses, the practical issues are access to Lara and Avakas, continued access to neighbouring properties and travel arrangements during construction.

Scope of works — Volume E, Appendix 100/2

Tender value and timetable

This is an open procedure for construction works, with the Department of Forests as the contracting authority. The €5.63 million figure is the initial procurement estimate; the final price will be established through the tender process.

Bidders may submit questions and requests for clarification until 15:00 on 24 November 2026. The contracting authority plans to respond by 2 December. The deadline for bids is 10:00 on 8 December 2026.

The results are expected to be announced three months after bid submission, with contract signing expected after four months. The works are to be completed within 13 months of the project start date.

The deadlines for bids and clarification requests are in Cyprus local time. The periods indicated for announcing the results and signing the contract are provisional. The construction timetable will depend on contract formalities, the project start date and environmental restrictions.

Timetable — Volume A, Section 2 of the tender documents

Environmental and planning procedures

The tender appendices contain documents from the project’s environmental review covering 2021–2026. These include earlier approvals, additional conditions issued in 2024, a review of compliance with conditions in 2025 and documents relating to revised drawings in 2026.

Of particular relevance is Appendix A8: a letter from the Department of Environment approving amended construction drawings subject to conditions. It forms part of this tender package. The letter requires compliance with previously established conditions, the provision of wildlife passages and on-site inspection of the first such structures. A works programme must also be submitted to the environmental authority.

This approval concerns specific drawings and carries conditions. Before work begins on site, the contracting authority and contractor must ensure that the applicable requirements are met. The status of the planning permit requires separate documentary clarification.

The review did not establish a link between this procurement and a specific entry in the Environmental Impact Assessment (EIA) register. The environmental discussion here therefore draws on the documents included with the tender itself.

Environmental documents — Volume E and Appendix A8

How the works will be organised and restricted

The documents provide for construction in sections. Before each stage begins, the contractor must submit a traffic management plan for approval, covering vehicle movements, pedestrian access and access to neighbouring properties.

Brief periods of alternating traffic controlled by portable traffic lights are permitted at narrow points. Full closures of individual sections will require approved diversions. Specific dates and traffic arrangements will become clearer once the works programme has been prepared.

Improvement works on coastal roads are prohibited from May to October, during the sea turtle breeding season.

Appendix 100/6 sets out separate restriction periods for 2027: March–October for the section marked Α on the plan, May–October for Γ and March–July for Δ. These letters identify construction sections within Phase A of the works being procured. They help establish when work may take place; the actual sequence will be set out in the works programme.

Works during the bird breeding season require coordination between the Department of Forests and the Game and Fauna Service, together with the latter’s written consent.

For necessary works in the Lara and Aspros Potamos areas during the turtle egg-laying season, the documents require coordination with the Department of Fisheries and Marine Research and its written consent. A separate clause retains the prohibition on coastal road improvements from May to October. The contracting authority still needs to clarify which specific works may be considered under the written-consent procedure while that prohibition remains in force.

The contractor must control dust, protect riverbeds and coastal vegetation, arrange waste removal and restore any natural drainage disrupted by the works.

Seasonal restrictions — Volume E, Appendix 100/6 and clauses 2.24–2.25

Questions to resolve before work begins

For park users, the outstanding practical details include the final sequence of works, temporary closure dates, diversion routes and access arrangements for the Lara car park. The documents already contain a table of permitted construction periods, but the dates on which the contractor will start work on each section remain to be set.

Any charge for entry or parking would require a separate official decision. The reviewed provisions on the scope of works and traffic management do not specify fees.

What to watch next

The next developments will be the contracting authority’s responses to bidders’ questions and any changes to the documents or deadlines. Attention will then turn to the number of bids received, their evaluation and the contractor selection decision.

Once the contract has been signed, the agreed price can be compared with the estimate and the construction timetable clarified. For Paphos residents, tourism businesses and visitors to Akamas, the most useful further updates will be access plans, work schedules for individual roads and arrangements for reaching Lara and Avakas.

Follow the tender on the official procurement portal